Proceed as follows when concreting in the anchors/erecting the base frame:
- Assemble the base frame and place it in its final position. Please observe the safety distances indicated in the installation instructions.
- Stake out the places around the posts where the base frame is to stand. Position the base frame so that all holes can be excavated easily. Tip: the holes should be approx. 70cm deep and have a diameter of around 30cm.
- Mount the anchors on the inside of the posts.
- Place the basic frame into its final position.
- The climbing frame must be horizontally level. You can use stones or wooden wedges to achieve this.
- Pour the ready-mixed concrete into the holes until they are filled to approx. 60cm. Make sure that only the anchors are covered with concrete, and that the posts remain free.
- When the concrete has set, you can fill in the rest with topsoil.
Please ensure that the supporting posts of your climbing frame are in contact with the ground when concreting them in. Correct anchorage is necessary for the stability of your climbing frame and helps to prevent danger spots. It also protects your screws from premature rusting.